Installation cost variance calculator
Put the planned cost of each part of an installation next to what it actually cost. The calculator shows where the money went over or under, so the next quotation can be priced from what really happens on site.
Free. No sign-up. Nothing you enter is saved or sent.
Planned and actual costs
| Cost line | Planned (₹) | Actual (₹) | Variance | Remove |
|---|---|---|---|---|
| +₹18,000 +1.6% | ||||
| +₹31,000 +22.1% | ||||
| -₹1,000 -2.9% | ||||
| +₹22,500 +37.5% | ||||
| +₹18,000 not planned |
Result
- Planned total
- ₹13,85,000
- Actual total
- ₹14,73,500
- Variance
- +₹88,500 (6.4%)
Over plan by more than 10%: Installation labour, Scaffolding and site costs, Civil rework. Price these from actual figures on the next quotation.
How to read this
- A positive variance means the job cost more than planned.
- Lines more than the threshold you choose over plan are flagged. A line with no planned cost is flagged if anything was spent on it.
- Use the same basis (before or after GST) for planned and actual figures.